The largest recreation project in Pickering’s history – complete with twin ice pads, which was on the chopping block as a way to cut costs last spring – remains on track with the approved schedule and scope, with council to hear a semi-annual update on the much-delayed Seaton Recreation Complex and Library Monday afternoon.
The city had deferred a final decision on the project in April of 2025 because of rising costs and tariff threats but a move to eliminate the ice pads concerned council members, who sent staff to prepare another report for the Sept. 29 meeting.
The long-term effects of U.S. President Donald Trump’s on-again, off-again tariffs had put a scare into city staff, with “challenging economic climate” cited by the city’s treasurer – who noted the high level of annual debt charges that the city would be responsible for – but a staff recommendation for a scaled down new community centre with the elimination of a twin-pad arena component was a bit too much fear-mongering for council, who sent them back to the drawing board.
Staff delivered several options to council in April, including the full lineup with the arena component at $266,365,000 and one that cut out the ice pads and came in at just over $243 million.
Dropping the arenas from the complex would mean keeping the ageing Don Beer Arena – scheduled to close when the Seaton Community Centre opens – beyond its shelf life and cost taxpayers nearly $600,000 a year in operating expenses and more than $19.4 million in deferred maintenance capital cost over the next ten years.
“We can be in a place where we have no Don Beer Arena and no back-up plan,” Ward 2 Councillor Mara Nagy said last year. “Folks in Pickering will be very disappointed if we don’t move forward with this.”
The project was first approved in January 2024 and has its ups and downs since then, including a denial of a $25 million ask from the federal Green and Inclusive Community Building program in early February.
Staff is currently meeting with federal and provincial representatives for additional funding and is also looking at naming rights for the facility.
Last September council endorsed the preferred schematic design and authorized staff to proceed to design development and production of contract documents. The project is currently still in the design development phase and remains on track for its completion by June 2026, when the project will move into the production of contract documents.
Engagement with staff happened between October 2025 to February 2026. Additional stakeholder engagement is scheduled from March to June of this year, focusing on sports user groups, the Pickering Public Library Board and the city’s advisory committees.
Two independent cost estimates will then be obtained: one prepared by the project architect and one prepared by a contracted project management support service consultant. Should the cost estimates show the project exceeds the approved budget, additional design revisions and value optimization could be required to bring the project cost into financial compliance.
The amenity list for all the community centre includes dedicated courts for basketball, pickleball and tennis, a skateboard park, splash pad, children’s playground, community gardens, a pavilion stage for events and an optional skating trail – in addition to the library, an aquatics centre with a 25-metre pool and separate warm-water leisure pool, fitness centre and studios and the two-pad arena.
The project will proceed into the production of contract documents in July.
The project is anticipated to be tender-ready in the first quarter of 2027. Construction was originally scheduled to begin this spring.
The report being delivered to council today is to provide “transparency” on next steps as the project progresses in detailed design.

PollView All
WIN A $100 GIFT CARD
Subscribe to INsauga’s daily email newsletter for a chance to win a $100 Amazon gift card.